In preparation for the new Fraser Common development, Matcon was contracted to demolish the existing 6 storey hotel.

client
Ledcor Construction Limited
client
location
Vancouver
Budget
$
  • Disposal and removal of all hazardous containing materials
  • Develop engineered demolition plans
  • Removal of all architectural finishes prior to demolition
  • Demolition of the existing concrete structure with heavy equipment, including High Reach Excavator
  • Removal of all footings and foundations
  • Removal and disposal of underground storage tanks (incl. pumping out contaminated liquids)
  • Periodic lane closure along Marine drive during critical demolition
  • LEED Project – 98% of all materials were recycled/reused
  • Slope cut perimeter and final rough grade of site