Extensive management of the works was required due to the site being located within an existing operational healthcare campus.

client
Bird Construction Ltd.
client

location
New Westminister
Budget
$
- Bulk/Detail Excavation of 82,000m3 of soils
- Installation of 550’ of 4” Pipe Piles
- Installation of 37,000sf of Shotcrete shoring & 32,000ft of tieback anchors
- Detail Backfill and Slab preparation
- Installation 2,750ft of #18 DCP Micropiles
See similar projects

Oakridge Park
An incredible opportunity to bring our expertise in demolition and excavation to such a landmark project in Vancouver.
Learn more
Gateway Residences
A demolition, remediation and excavation project all in preperation for development.
Learn more
Lumina Brentwood - 2425 Beta Ave
A dynamic project featuring the tag team efforts of our Civil and Environmental divisions.
Learn more
Mountain Highway Interchange
Fast paced and focused, this lifeline to North and South of Vancouver was a fun project for our excavation and shoring teams.
Learn more