A dynamic excavation and shoring effort to prepare for backfill and slab preparation for the Brentwood Town Centre development.

- Bulk/Detail Excavation of 76,800m3
- Installation of 28,000sf of shotcrete shoring
- Installation of 16,500sf of 8 inch underpinning
- Installation of 63,500ft of tieback anchors
- Detail Backfill and Slab preparation
- To reach parking level 7 (75 feet deep) a telescopic excavator was required to remove the remaining soil.
See similar projects

Oakridge Park
An incredible opportunity to bring our expertise in demolition and excavation to such a landmark project in Vancouver.
Learn more
Gateway Residences
A demolition, remediation and excavation project all in preperation for development.
Learn more
Mountain Highway Interchange
Fast paced and focused, this lifeline to North and South of Vancouver was a fun project for our excavation and shoring teams.
Learn more
Tower 3 Brentwood Mall
A dynamic excavation and shoring effort to prepare for backfill and slab preparation for the Brentwood Town Centre development.
Learn more