A multidisciplinary project requiring demolition, excavation and deep foundation all while protecting existing infrastructure and a vital transit corridor.

client
Ledcor Construction Limited
client

location
Surrey
Budget
$
- 100,000 cubic meters of excavation.
- 20,000 square feet of shotcrete.
- 16,000 lineal feet of conventional anchors.
- 26,000 square feet of poly & mesh.
- 80,000 square feet of slab preparation.
- work below existing King George Skytrain Station.
- demolition of existing hotel.
See similar projects

Oakridge Park
Incredible opportunity to bring our expertise in demolition and excavation to such a landmark project in Vancouver.
Learn more
Trans Mountain Expansion Project
Installation of permanently anchored shotcrete shoring walls at the Burnaby Terminal.
Learn more
1500 Robson
Retained to excavate and prep for development of a 127 unit multi residential tower.
Learn more
Evergreen Line
An intricate project requiring contaminated soil management, temporary road reinstatements and managing operations around high voltage overheas lines.
Learn more