This Project Involved:
- Installation of storm, sanitary & water including services to 171 lots.
- Excavation & haulage of 41,000m³ after heavy earthwork operations were complete.
- Supply & install of all BCH, Shaw & Telus conduits & structures.
- Trenching & backfilling for Fortis BC.
- Installation of electrical streetlighting works.
- Sub-contracted 27,000m² of asphalt placement for all roads.