This Project Involved:
- Commission the excavation and soil retention design;
- Temporary re-routing of all utilities within the excavation footprint and temporary removal of light standard;
- Excavate to 7m in depth to remove PCE and TCE impacted soils within an operational Safeway carpark;
- Excavation, transport and disposal of ~4,300 MT of contaminated soil;
- Installation of 3,600 sf shotcrete and shoring;
- Drilling and installation of 1,270 lineal ft of soil anchors;
- Underpinning Safeway sign;
- Slot cut final stage of excavation;
- Import, place and compact ~4,100MT of structural backfill;
- Reinstate utilities and Carpark.